Jiangsu, China
Ann@nexympure.com
Coal Chemical · Demineralized Water & Water Reuse

Xinjiang Zhongneng Wanyuan Chemical Demineralized Water & Reclaimed Water Membrane Systems

Two systems were retrofitted in one campaign: demineralized water at 145 m³/h design capacity and reclaimed water at 70 m³/h. After start-up, salt rejection held above 99% with permeate conductivity down to 3.2–3.5 μS/cm.

  • Location Manas, Changji, Xinjiang
  • Scale 2 systems
  • Commissioned 2024-04
Coal ChemicalTwo-Pass ROReclaimed Water ReuseFouling-Resistant Membrane
Illustrative view of a reverse osmosis system inside a coal chemical plant building
Illustrative view: horizontal pressure vessels on multi-tier skids together with high-pressure pumps, corresponding to the demineralized water and reclaimed water systems.
145Demineralized water design m³/h
>99System salt rejection %
3.2–3.5Permeate conductivity μS/cm
80System recovery %
01

Project Overview

Client, scale, feed water and project background

Xinjiang Zhongneng Wanyuan Chemical is located in the Manas County industrial park of Changji Prefecture. Its process units demand high demineralized water quality and uninterrupted supply, while the park also sets explicit targets for wastewater reuse rate. This retrofit covered both the reverse osmosis system at the demineralized water station and the reclaimed water RO system, using a single fouling-resistant membrane model across two very different feed conditions.

The demineralized water system treats feed of about 477 μS/cm with moderate total hardness and alkalinity; the reclaimed water system receives about 1771 μS/cm with total hardness of 790 mg/L plus a certain load of organics and ammonia nitrogen, placing far higher demands on fouling resistance. QC-LP-8040-400FR elements were selected, loaded in a two-stage arrangement with inter-stage boosting to balance flux between stages.

Membrane elements arrived on site on 14 April 2024; installation, flushing and soaking followed immediately, commissioning began on 15 April, and a continuous 72-hour assessment run started on 17 April: first-pass second-stage output exceeded 90 m³/h, total output across stages one to three exceeded 103 m³/h, concentrate 26 m³/h, recovery 80%, feed conductivity 356 μS/cm and permeate conductivity 3.2–3.5 μS/cm, with salt rejection above 99% — meeting the owner's assessment requirements.

Client
Xinjiang Zhongneng Wanyuan Chemical Co., Ltd.
Location
Manas County Industrial Park, Changji Prefecture, Xinjiang
Project type
RO membrane replacement for demineralized water / reclaimed water reuse
System scale
2 systems (demineralized 145 m³/h, reclaimed 70 m³/h)
Feed water
Demineralized: process water (477 μS/cm); Reclaimed: park reclaimed water (1771 μS/cm)
Product water use
Boiler make-up water / process water / wastewater reuse
Membrane elements
QC-LP-8040-400FR, 6-element pressure vessels, 2 stages
Commissioning
April 2024
02

Process Design

System flow, design boundaries and key control points

01Raw water / reclaimed water
→
02Multi-media filtration + UF
→
03Cartridge filter
→
04High-pressure pump
05First-pass RO
→
06Second-pass RO
→
07Demineralized tank / reuse basin
→

Both systems share the same pretreatment + two-pass RO framework; the reclaimed water train strengthens pretreatment and antiscalant dosing to address high hardness and high COD, controlling scaling and biofouling on the membrane surface.

One membrane model covering two duty conditions

The demineralized and reclaimed water systems use the same fouling-resistant model, simplifying spare parts and O&M; different feed salinities are accommodated by adjusting the arrangement and recovery rate.

Two-stage arrangement with inter-stage boosting

A roughly 2:1 first-stage arrangement with inter-stage boosting balances flux and differential pressure between stages, avoiding scaling on the second-stage concentrate side and rapid flux decline.

Antiscalant strategy for high-hardness reclaimed water

With total hardness of 790 mg/L, antiscalant dosing and recovery control (70%) keep the LSI below the scaling risk threshold.

Assessed on a continuous 72-hour run

Acceptance is judged on permeate flow, conductivity and recovery over 72 continuous hours rather than instantaneous readings, ensuring the data represent long-term operating performance.

03

Key Equipment & Membrane Configuration

Membrane models, loading arrangement and auxiliary equipment

SystemMembrane modelLoading arrangementDesign permeateKey feed indicators
Demineralized waterQC-LP-8040-400FR2 stages, 6-element vessels145 m³/h (assessed ≥103 m³/h)Conductivity 477 μS/cm
Reclaimed water reuseQC-LP-8040-400FR2 stages, 6-element vessels70 m³/hConductivity 1771 μS/cm, total hardness 790 mg/L
AuxiliariesCartridge filter, high-pressure pump, inter-stage booster pump, antiscalant / reducing agent dosing———

Element counts for both systems follow the on-site pressure vessel specification (6 elements, 2 stages); refer to the as-built list for exact quantities.

04

Operating & Acceptance Data

Field measurements versus contractual guarantee values

Table 1 Assessment criteria versus measured results for the two systems
Assessment itemContractual / design guaranteeMeasured at acceptanceVerdict
Demineralized water output≥103 m³/h (stages 1–2 ≥90 m³/h)Stages 1–2 >90, stages 1–3 >103 m³/hPass
Demineralized salt rejection≥99% within 1 year, ≥98% within 3 years>99%Pass
Reclaimed water output≥70 m³/hDesign value achievedPass
Reclaimed salt rejection≥98% within 1 year, ≥96% within 3 yearsGuarantee achievedPass
System recoveryDemineralized 80%, reclaimed 70%80% / 70%Pass
Permeate conductivity—3.2–3.5 μS/cm (feed 356 μS/cm)Excellent
Continuous run assessment72 hours72 hours continuous, parameters stablePass

Concentrate discharge from the demineralized water system is 26 m³/h at 80% recovery; the reclaimed water system is controlled at 70% recovery to suppress scaling. Data above are taken from the 72-hour continuous operating record starting 17 April 2024.

05

Project Results

Client acceptance conclusions and reusable engineering experience

✓

Two systems delivered in one campaign

Membrane replacement and commissioning for both systems were completed within a single shutdown window, shortening plant downtime.

✓

Marked improvement in product water quality

Permeate conductivity of 3.2–3.5 μS/cm with salt rejection above 99% satisfies boiler make-up and process water requirements.

✓

Reuse rate meets park targets

The reclaimed water system runs stably at 70% recovery, cutting both fresh water intake and wastewater discharge.

✓

Experience gained on high-hardness reclaimed water

A complete parameter set of enhanced pretreatment + antiscalant control + inter-stage boosting has been established for high-hardness, high-COD reclaimed water.