Thermal Power · Boiler Make-up Water

Shaanxi Coal Chemical Xiantao Clean Energy Power Plant Demineralized Water System

A two-phase demineralized water system using two-pass RO + EDI: phase 1 at 30 m³/h × 2 (132 elements) and phase 2 at 40 m³/h × 2 (232 elements), with permeate conductivity held steady at 8 μS/cm. Accepted in August 2023.

  • Location Xiantao, Hubei
  • Scale 30 / 40 m³/h × 2
  • Accepted 2023-08-17
Thermal PowerTwo-Pass RO + EDIBoiler Make-up WaterTwo-Phase Build
Illustrative view of two-pass RO and EDI in a power plant chemical water hall
Illustrative view: two-pass RO skids with EDI modules and control cabinets, corresponding to a power plant chemical water hall.
8Permeate conductivity μS/cm
132 / 232Elements in two phases
43Phase 2 system output m³/h
24hContinuous operation
01

Project Overview

Client, scale, feed water and project background

The demineralized water preparation system at the power plant of Shaanxi Coal Chemical Xiantao Clean Energy Co., Ltd. supplies boiler make-up water, with a mixed feed of groundwater and tap water. The project was built in two phases: phase 1 at 30 m³/h × 2 with 132 elements (36 × 2 first pass, 30 × 2 second pass); phase 2 at 40 m³/h × 2 with 232 elements (74 × 2 first pass, 42 × 2 second pass).

The process is groundwater → pretreatment → first-pass RO → second-pass RO → EDI, a two-pass RO plus electrodeionization route whose product water goes directly to boiler make-up, operating 24 hours a day continuously. With a mixed groundwater and tap water feed, a reducing agent and an antiscalant are dosed to control residual chlorine and scaling risk.

Both phases were contracted on 4 August 2023; installation started on 14 August and was completed on 16 August, with operation qualified and acceptance organized on 17 August. Permeate conductivity held steady at 8 μS/cm, system output reached 30 m³/h and 43 m³/h respectively, operation was good with no abnormalities, and the owner signed off.

Client
Shaanxi Coal Chemical Xiantao Clean Energy Co., Ltd.
Location
Xiantao, Hubei Province
Project type
Power plant demineralized water preparation system (two phases)
System scale
Phase 1 30 m³/h × 2; Phase 2 40 m³/h × 2
Feed water
Mixed groundwater and tap water
Product water use
Boiler make-up water
Membrane elements
QC-LP-8040-400 (132 in phase 1; 232 in phase 2)
Acceptance date
17 August 2023
02

Process Design

System flow, design boundaries and key control points

01Groundwater / tap water
→
02Pretreatment (multi-media + cartridge filtration)
→
03Reducing agent / antiscalant
→
04First-pass RO
05Second-pass RO
→
06EDI
→
07Demineralized tank
→
08Boiler make-up water

Two-pass RO brings permeate conductivity down to a level EDI can accept; EDI then provides continuous polishing demineralization without acid or caustic regeneration, suiting continuous power plant operation.

Progressive scaling across two phases

Phase 1 at 30 m³/h × 2 met initial unit demand and phase 2 expanded to 40 m³/h × 2, with elements rising from 132 to 232, avoiding an oversized one-off investment.

Two-pass RO combined with EDI

The first and second RO passes share the desalination load in stages, so EDI only treats low-conductivity feed, making module life and product resistivity more stable.

Dual dosing of reducing agent and antiscalant

For residual chlorine and hardness in groundwater, a reducing agent protects the polyamide membrane while an antiscalant controls concentrate-side scaling.

Permeate conductivity as the core control indicator

System rejection is not assessed separately; permeate conductivity of 8 μS/cm is the core control indicator, directly corresponding to boiler make-up water quality.

03

Key Equipment & Membrane Configuration

Membrane models, loading arrangement and auxiliary equipment

Table 1 Scale and membrane configuration of the two phases
PhaseSystem scaleMembrane configurationSystem outputPermeate conductivity
Phase 130 m³/h × 2132 elements (36 × 2 first pass, 30 × 2 second pass)30 m³/h8 μS/cm
Phase 240 m³/h × 2232 elements (74 × 2 first pass, 42 × 2 second pass)43 m³/h8 μS/cm

Membrane model QC-LP-8040-400; both phases use two-pass RO + EDI and operate 24 hours continuously.

04

Operating & Acceptance Data

Field measurements versus contractual guarantee values

Table 2 Implementation and acceptance records of the two phases
ItemPhase 1Phase 2
Contract signed2023-08-042023-08-04
Installation started2023-08-142023-08-14
Installation completed2023-08-162023-08-16
Acceptance date2023-08-172023-08-17
System permeate flow30 m³/h43 m³/h
Permeate conductivity8 μS/cm8 μS/cm
Operating statusGood, no abnormalitiesGood, no abnormalities

Both phases were installed and accepted within 12 days of contract signing, with permeate conductivity steady at 8 μS/cm. Per the owner's requirement, system rejection is not assessed separately; permeate conductivity is the acceptance criterion.

05

Project Results

Client acceptance conclusions and reusable engineering experience

✓

Both phases delivered quickly

Only 13 days from contract signing to acceptance, meeting the power plant's boiler make-up water commissioning milestone.

✓

Stable product water quality

Permeate conductivity of 8 μS/cm satisfies boiler make-up requirements over the long term, with no abnormal system operation.

✓

Expansion without changing the process framework

Phase 2 scaled the membrane configuration proportionally on the phase 1 process basis, reducing duplicated design and spare part variety.

✓

A standard configuration for power plant demineralized water

Two-pass RO + EDI together with the dual dosing strategy can serve as the reference configuration for comparable power plant demineralized water systems.