Jiangsu, China
Ann@nexympure.com
Coking · Power Plant Boiler Make-up Water

Hejin Yumenkou Coking 1.72 Mt/a Coking Project Demineralized Water Station

Serving the boiler make-up water of the power plant attached to a 1.72 Mt/a coking project, the 2 × 80 m³/h demineralized water station was fully re-membraned using multi-media filtration + UF + two-pass RO + EDI, achieving permeate conductivity of 47.6–55 μS/cm.

  • Location Hejin, Yuncheng, Shanxi
  • Scale 2 × 80 m³/h
  • Accepted 2022-09
CokingBoiler Make-up WaterTwo-Pass RO + EDIFull Station Change-out
Illustrative view of a demineralized water station at a coking plant
Illustrative view: RO skids, EDI modules and ion exchange vessels arranged as a complete train, corresponding to the demineralized water station building.
2 × 80Station capacity m³/h
98.5–98.8Salt rejection %
≈75Recovery %
≤4000Feed conductivity μS/cm
01

Project Overview

Client, scale, feed water and project background

The power plant attached to the 1.72 Mt/a coking project of Hejin Yumenkou Coking Co., Ltd. uses boiler make-up water as its main water demand. Performance of the elements in the demineralized water station had decayed, requiring a full station membrane change-out. The station is sized at 2 × 80 m³/h and fed with local tap water.

The process is pretreatment (multi-media filtration MMF) + ultrafiltration (UF) + two-pass RO + EDI, where EDI handles polishing demineralization and continuous production. EDI places demanding requirements on RO permeate conductivity and its stability, since the stability of the RO section directly determines EDI operating current and product resistivity.

The contract was signed in September 2022, with both parties agreeing to start on site on 20 September; the units were handed over for trial operation after installation. Assessment was performed under stable feed quality at conductivity ≤4000 μS/cm: minimum rejection ≥98% within the warranty period, ≥95% over service life, nitrogen removal ≥80% over service life, guaranteed element service life ≥3 years, membrane flux ≤18 lmh, RO flushing interval ≥24 h and chemical cleaning interval ≥30 days.

Client
Hejin Yumenkou Coking Co., Ltd. (1.72 Mt/a coking project)
Location
Hejin, Yuncheng, Shanxi Province
Project type
RO membrane replacement at the demineralized water station (2 units)
System scale
2 × 80 m³/h
Feed water
Local tap water (conductivity ≤4000 μS/cm)
Product water use
Power plant boiler make-up water
Process
Pretreatment (MMF) + UF + two-pass RO + EDI
Acceptance date
September 2022
02

Process Design

System flow, design boundaries and key control points

01Tap water
→
02Multi-media filter MMF
→
03Ultrafiltration UF
→
04Cartridge filter
05First-pass RO
→
06Second-pass RO
→
07EDI
→
08Demineralized tank
09Boiler make-up water
→
→
→

EDI is sensitive to CO₂ and conductivity in its feed; the stability of second-pass RO permeate conductivity is the key control point for the resistivity of the station's final product water.

Two-pass RO as the EDI safeguard

The second RO pass holds permeate conductivity at 47.6–55 μS/cm, giving EDI a low-load, low-conductivity feed and extending EDI module life.

MMF + UF dual pretreatment

Multi-media filtration removes suspended solids and part of the organics, while UF further controls SDI to meet the element requirement of SDI ≤5.

Dual constraint of flux and cleaning interval

Designed at membrane flux ≤18 lmh together with flushing interval ≥24 h and chemical cleaning interval ≥30 days, keeping operating intensity within the membrane manufacturer's recommended range.

Full station change-out with parameter re-calibration

After replacement, recovery and inter-stage pressure were re-calibrated on both systems so that permeate deviation between the two units stays controllable under the same feed conditions.

03

Key Equipment & Membrane Configuration

Membrane models, loading arrangement and auxiliary equipment

Table 1 Contractual technical indicators and acceptance results
ItemDesign / contractual requirementMeasured at acceptance
System scale2 × 80 m³/h2 units in parallel
Process routeMMF + UF + two-pass RO + EDIBuilt to drawing
Rejection within warranty period≥98%98.5%–98.8%
Rejection over service life≥95%Achieved
Nitrogen removal over service life≥80% (operating pH <7)Achieved
Membrane element service life≥3 yearsPer contract guarantee
Membrane flux≤18 lmhDesign value compliant
Flushing / chemical cleaning interval≥24 h / ≥30 daysExecuted per procedure

Feed is assessed at conductivity ≤4000 μS/cm; 'Achieved' above means the acceptance record confirms the contractual value was met.

04

Operating & Acceptance Data

Field measurements versus contractual guarantee values

Table 2 Acceptance operating data of the two systems
Operating indicatorSystem 1#System 2#
Feed conductivity μS/cm38703870
Permeate conductivity μS/cm47.655.0
Salt rejection %98.898.5
Feed pressure MPa1.321.38
Inter-stage pressure MPa1.251.28
Concentrate pressure MPa1.11.1
Recovery %74.975.9

Operating data of both systems met the acceptance criteria. Recovery is controlled at around 75%, balancing permeate output against scaling risk.

05

Project Results

Client acceptance conclusions and reusable engineering experience

✓

Successful start-up after a full station change-out

Both 80 m³/h systems went straight into trial operation after installation, with no element leakage or permeate shortfall.

✓

Improved EDI feed conditions

RO permeate conductivity of 47.6–55 μS/cm provides EDI with a stable low-conductivity feed, restoring product resistivity to design level.

✓

All contractual indicators met

Rejection of 98.5%–98.8% exceeds the 98% warranty requirement; flux, cleaning interval and other operating constraints all stayed within design range.

✓

Complete experience for coking water stations

A full station change-out and parameter calibration method for MMF + UF + two-pass RO + EDI has been established, transferable to comparable coking power plant projects.